July 2019 Roads Division Construction Schedule and Updates

Monday, July 1, 2019

Updated 7/10/2019

Benton County Roads Division is out this week preparing roads for next week’s chip seals.

Weather delayed chip seals starting in North Albany on Monday, July 8, 2019. Roads will have temporary signs one to two days in advance with dates of chip seals. The revised schedule is listed below. 

July 10th – Shannon Drive, Kouns Rd., Granger, Overlook and Kainui

July 11th – Pettibone

July 12th – Camp Adair

July 15th – Stone Ridge and Dumbeck

Starting the week of July 22, 2019, Airport and Sexton Roads will undergo a one-day stabilization process that includes rocking and grading.

The Skunk Creek Culvert Replacement on Oak Creek Drive starts the week of July 22, 2019 also. Beginning Monday, August 5, 2019 the road will be closed at milepost 2.05 on Oak Creek Drive. A 1,000 foot bypass will be built at the site to detour traffic. It is anticipated that the road will be closed approximately 15 days.