Bellfountain Road Bridge

Project ID: 
Bellfountain Road Bridge
Project Type:
Bridge
Project Status: 
Completed
Date Received: 
Tuesday, November 7, 2017
Location: 
Bellfountain Road Bridge

All work is complete.

Bridge was replaced summer 2016.  Road was also raised to reduce impact of flooding to travelling public.

Cost : $350,000 (Original bridge project)

Funding : Motor Fuel Tax

Contractor : Benton County Public Works

For more information about the project, those interested can contact Civil Engineer Fred Gomez at 541-766-6821 or by email at fred.gomez@co.benton.or.us

Removing the old bridge
Driving piling for the new bridge
North bent has been poured and is curing
Pouring the second bent
Placing the bridge deck
Placing the bridge deck
Placing the bridge deck
Status Updates

Last Updated : July 21, 2017

- Bridge will be repaved Week of September 24

- October 7, 2016 - Final shoulder rock was placed, bridge is open.

- September 30, 2016 - Bridge is complete and ready for use.

- September 19, 2016 - Paving to begin

- September 6, 2016 - Bridge decks to be placed

- August 16, 2016 - Roadway being removed and rebuilt

- August 15, 2016 - Both bents have been poured

- July 25, 2016 - Bridge has been removed, piles have been set

 - July 18,2016 - Construction Begins

- Spring 2016 - Obtained final permits 

- January 2016 - Completed Design